Project charter
Project management training for team leads
- Project manager
- Aisyah Rahman, HR manager
- Sponsor
- Tan Wei Ming, Operations director
- Start
- 1 Feb 2027
- End
- 31 May 2027
Purpose
Team leads run most of our projects without any formal training, and handovers between them are inconsistent. This project gives twenty team leads one shared way of scoping, estimating and reporting work.
Objectives
- All twenty team leads complete the course by 30 April
- Every live project has a written scope and a schedule in the shared format by 31 May
- Status reports to the operations director use one template from May
In scope
- A three-day course for twenty team leads
- Adoption of a shared scoping and status-report template
- A 30-day follow-up check with each team lead
Out of scope
- Exam preparation or certification
- Training for staff who are not team leads
- A new project management software purchase
Deliverables
- Training delivered to all twenty team leads
- The shared scope and status-report templates
- A follow-up findings note for the sponsor
Success measures
- Twenty of twenty complete the course
- Every live project has a written scope by 31 May
- Sponsor receives all May status reports in the new format
Milestones
| Charter approved by the sponsor | 5 Feb 2027 |
| Grant application submitted | 26 Feb 2027 |
| Training delivered | 23 Apr 2027 |
| Follow-up checks complete | 28 May 2027 |
Budget
RM40,000 · Company training budget, with an HRD Corp grant claim
Key stakeholders
- Tan Wei Ming, Operations director: sponsor
- Aisyah Rahman, HR manager: project manager
- Team leads: participants
- Finance: budget and grant claim
Assumptions
- All twenty team leads can be released for three days
- The grant is approved before the training date
Constraints
- Training must finish before the Q2 planning cycle
- Budget is capped at the figure above
Key risks
- Team leads are pulled back to urgent work during the course
- Grant approval is slower than planned
- Templates are not used after the course
Approval
Sponsor, project manager: name, signature and date lines are added to the downloaded document.